DRRM · DRRM-2026-04
Mayon Eruption Emergency Response 2026
DelayedRelief Round 2 is two weeks late — rice supplier short by 180 sacks.
Phases
Scroll sideways on a phone.
-
Rapid needs assessment
May 15, 2026 – May 25, 2026
-
Relief Round 1 — food & sleeping kits
May 20, 2026 – Jul 15, 2026
-
Relief Round 2 — food & hygiene kits
Jul 16, 2026 – Oct 15, 2026
-
WASH & psychosocial support
Jun 1, 2026 – Nov 30, 2026
-
Early recovery — cash-for-work
Nov 1, 2026 – Dec 15, 2026
Today, Oct 29, 2026
Phase progress
Update each phase as the work moves
-
Rapid needs assessment
Done100% -
Relief Round 1 — food & sleeping kits
Done100% -
Relief Round 2 — food & hygiene kits
Late78% -
WASH & psychosocial support
In progress45% -
Early recovery — cash-for-work
Upcoming0%
Milestones
Key dates the donor report tracks
-
Needs assessment report submitted
May 25, 2026
-
Round 1 complete — 2,140 families
Jul 15, 2026
-
Round 2 complete
Oct 15, 2026 · overdue
-
Caritas Philippines interim report due
Nov 15, 2026
-
Project close-out
Dec 15, 2026