Mayon Eruption Emergency Response 2026

Delayed
May 15, 2026 – Dec 15, 2026 Camalig, Guinobatan, Malilipot, Tabaco City You are here

Phases

Scroll sideways on a phone.

Phase
MayJunJulAugSepOctNovDec
  • Rapid needs assessment

    May 15, 2026 – May 25, 2026

  • Relief Round 1 — food & sleeping kits

    May 20, 2026 – Jul 15, 2026

  • Relief Round 2 — food & hygiene kits

    Jul 16, 2026 – Oct 15, 2026

  • WASH & psychosocial support

    Jun 1, 2026 – Nov 30, 2026

  • Early recovery — cash-for-work

    Nov 1, 2026 – Dec 15, 2026

Today, Oct 29, 2026

Phase progress

Update each phase as the work moves

  • Rapid needs assessment

    Done
    100%
  • Relief Round 1 — food & sleeping kits

    Done
    100%
  • Relief Round 2 — food & hygiene kits

    Late
    78%
  • WASH & psychosocial support

    In progress
    45%
  • Early recovery — cash-for-work

    Upcoming
    0%

Milestones

Key dates the donor report tracks

  1. Needs assessment report submitted

    May 25, 2026

  2. Round 1 complete — 2,140 families

    Jul 15, 2026

  3. Round 2 complete

    Oct 15, 2026 · overdue

  4. Caritas Philippines interim report due

    Nov 15, 2026

  5. Project close-out

    Dec 15, 2026