Phase
JulAugSepOctNovDecJanFebMarAprMayJun
  • Household profiling & selection

    Jul 1, 2026 – Jul 31, 2026

  • Skills training

    Jul 15, 2026 – Sep 30, 2026

  • Starter kit distribution

    Aug 10, 2026 – Nov 30, 2026

  • Savings group formation

    Aug 15, 2026 – Dec 15, 2026

  • 120-day monitoring

    Dec 1, 2026 – Apr 30, 2027

  • Impact assessment & close-out

    May 1, 2027 – Jun 30, 2027

Today, Oct 29, 2026

Phase progress

Update each phase as the work moves

  • Household profiling & selection

    Done
    100%
  • Skills training

    Done
    100%
  • Starter kit distribution

    In progress
    47%
  • Savings group formation

    In progress
    73%
  • 120-day monitoring

    Upcoming
    0%
  • Impact assessment & close-out

    Upcoming
    0%

Milestones

Key dates the donor report tracks

  1. 300 households profiled

    Jul 31, 2026

  2. Training complete — 286 attended

    Sep 30, 2026

  3. All starter kits delivered

    Nov 30, 2026

  4. DKA interim report due

    Jan 15, 2027

  5. Project close-out

    Jun 30, 2027