Livelihood · LIV-2026-02
Integrated Livelihood (INELP) — Cohort 3
On trackPhases
Scroll sideways on a phone.
-
Household profiling & selection
Jul 1, 2026 – Jul 31, 2026
-
Skills training
Jul 15, 2026 – Sep 30, 2026
-
Starter kit distribution
Aug 10, 2026 – Nov 30, 2026
-
Savings group formation
Aug 15, 2026 – Dec 15, 2026
-
120-day monitoring
Dec 1, 2026 – Apr 30, 2027
-
Impact assessment & close-out
May 1, 2027 – Jun 30, 2027
Today, Oct 29, 2026
Phase progress
Update each phase as the work moves
-
Household profiling & selection
Done100% -
Skills training
Done100% -
Starter kit distribution
In progress47% -
Savings group formation
In progress73% -
120-day monitoring
Upcoming0% -
Impact assessment & close-out
Upcoming0%
Milestones
Key dates the donor report tracks
-
300 households profiled
Jul 31, 2026
-
Training complete — 286 attended
Sep 30, 2026
-
All starter kits delivered
Nov 30, 2026
-
DKA interim report due
Jan 15, 2027
-
Project close-out
Jun 30, 2027